City of Chehalis Public
Works Department
Contact:
Tim Grochowski, Public Works Director 360.748.0238
SUBJECT:
Listed below
are the activities/progress that the contractor expects
to complete on the Chamber Way Project during the next two week
period:
The
contractor continues to make good progress, due to the good weather conditions
and good work practices. The scheduled work will necessitate
various lane closures and the closure of the right turn lane of State Ave
(eastbound) onto Chamber Way for the contractor’s and the public’ safety, and
allow the contractor to complete his work quicker. The closures will be intermittent and
flaggers will used to help traffic navigate this area
as needed.
f
the workers.on will be at the asphalt construction area to aid the vehicles and
for the safetey ng these ramps to vehicles, t
When the asphalt work begins on the I-5
ramps, the contractor will not be closing the ramps to vehicles as there will be
a minimum of 14-feet of travel lane for the public to use. A flag person will be site for the
safety of the workers and the traveling public.